PUBLIC NOTICE NO.44/2002 Date: 22.04.2002
Disposal of the pending drawback claims-reg.
All Exporters, Importers, Custom House Agents and the trade are
informed that this Custom House has been making all efforts for disposal of the
pending drawback claims. The list of all old claims in which deficiency memo has
been issued are being forwarded to Bombay Custom House Agent’s Association,
Delhi Exporters Association in floppy for wide publicity among the members of
exporters.
It is reiterated that the exporters should reply to the queries. In cases
where the claims are beyond 6 months from now, they are also required to submit
the Bank realization certificate in respect of the export consignment pertaining to
particular claim.
In order to expedite disposal of pending drawback cases, the exporters
should submit their replies alongwith Bank realisation certificate within 15 days of
the Public Notice to the CFS Mulund, failing which their claims may be treated as
unsubstantiated and liable for rejection, or may be considered for lower rate, if so
admissible.
Sd/-22.04.2002
(RAMESH RAMCHANDRAN)
COMMISSIONER OF CUSTOMS (GENERAL)
Issued from F.No. S/1034-DBK/2002 CFS (M)