5.11.1
Extension of Export Obligation Period
The firm /company, which is applying for registration with BIFR/Rehabilitation Department of State Government, shall also intimate DGFT with regard to relief sought for EPCG authorization, if any within 30 days of receipt of application by agency concerned.
DGFT, thereafter, shall take up the matter with agency concerned to safeguard government interest on account of default in fulfillment of export obligation imposed on EPCG authorization obtained by such firm/companies.
DGFT may consider such application for grant of period of extension upto 12 years, or as per rehabilitation package prepared by operating agency and approved by BIFR board/ state authority.