4.16
Time limit for fixation of norms by Norms Committees
(i) Where norms are not finalised by Norms Committee within four months from the date of receipt of complete application along with documents / technical details as per Appendix 4E, norms as applied for may be treated as final.
(ii) In case application for fixation of adhoc norms / SION is rejected on ground of non-furnishing of required documents/ information to Norms Committee or technical authority represented in Norms Committee, authorisation holder shall be liable to pay customs duty with interest as notified by DoR and amount as per paragraph 4.49(a)(ii). In case SION for the said product is notified, SION would be made applicable for deciding wastage norms and EO.
(iii) In cases where entitlement of the applicant for grant of Advance Authorisation as per paragraph 4.12 was lower than the quantity of input applied by the applicant under Advance Authorisation and export obligation is completed pending fixation of norms by Norms Committee, entitlement for authorisation as given in paragraph 4.12 may be re-credited upon production of documentary evidence (copies of Shipping bill / bill of export/_Tax invoice for supply prescribed under GST rules) showing fulfilment of export obligation in respect of previous authorisations. However, bond waiver / redemption shall not be allowed pending fixation of norms in such cases.
(Above sub-para (iii) has been amended vide PUBLIC NOTICE NO.26/2017, DT. 20/09/2017)
[OLD- (iii) In cases where entitlement of the applicant for grant of Advance Authorisation as per paragraph 4.12 was lower than the quantity of input applied by the applicant under Advance Authorisation and export obligation is completed pending fixation of norms by Norms Committee, entitlement for authorisation as given in paragraph 4.12 may be re-credited upon production of documentary evidence (copies of Shipping bill / bill of export / Central Excise certified copies of invoices) showing fulfilment of export obligation in respect of previous authorisations. However, bond waiver / redemption shall not be allowed pending fixation of norms in such cases.]