Circular No. 409/42/98-CX dated 14/7/1998
Subject: Disputes between CBEC and PSUs - Clearance by the Committee
on Disputes
As you are aware, in pursuance of the Supreme Court"s decision for reducing litigation
between one Govt. Department and another, a Committee on Disputes was created in the
Cabinet Sectt. to examine the disputes and give clearance or otherwise to pursue the
litigation. Accordingly, Board started receiving a number of proposals from different
Commissionerates. In this connection please refer to Board"s Circular No. 329/45/97-CX
dated 14.8.97 (enclosed).
2. However, in the recent past, the Board has noticed that such proposals are sent to
Board only after the Commissionerate"s appeals were dismissed by the CEGAT as no
clearance were obtained from the COD to pursue the dispute. This results in unnecessary
delay in pursuing the matter in the CEGAT etc. Therefore, it is reiterated that in all
such cases where the Department has filed appeals in CEGAT etc. immediate action may
be taken to obtain the clearance from the CODs. In this connection it may be ensured
that a self contained proposal may be sent in /each case to the Board alongwith the
following documents:
1. 20 copies of "Brief in the prescribed format (copy enclosed)
2. Four copies of Order in Appeal
3. Four copies of Order in Original
4. A copy of Memorandum of Appeal filed/to be filed in CEGAT
5. Copies of other relevant documents.
The above instructions may please be followed strictly.
Sd/-
(A.K.Roy)
Deputy Secretary (Review)
No.l37/48/95-CX dated 18.7.95). It has been decided by the Board that the requests of
the assessees in this regard should be attended in time-bound manner so, as to dispose
of such cases within one month of the submission on the request.
Sd/-
(S.K. Sinha)
Under Secretary to the Government of India
F.No. 267/58/98-CX-8